The athletic director at Liberty High is planning the bunch of the school’s track and field team. The first team practice is scheduled for April 1. The activities, their Immediate predecessors, and the activity time estimates (In weeks) are listed in the following table.
Immediate Predecessor Most Probable Order team equipment Reserve buses for meets The project network is depicted in the following diagram. Please download this worksheet, and upload it once you input your answers to the following questions.
3. 12 points/Compute the expected time and variance for sach activity. Round your answers to two decimal places.
07 poines Using the expected times determined in part a compute the earliest time for eich activity. What is the eritical path, the expected project completion tome, and the variance for the project?
14 points If the athietic director plans to start the project on January 1, calculate the probability the track and fleld leam will be ready by the scheduled April 1 date. Give your answer to four decimals or two decimals if written as a percentage. For example 0.1234 or 32.347